A Hazard and Operability Study for Assessing Hazard Risks using Fault Tree Analysis in an Iranian Petrochemical Industry Unit (2016)
Marzieh Kosari1, Sakineh Mahdavi2, Vida Zaroushani 3*, Tahereh Dehghani4 , Zahra Naghavi Konjin5
1. BSc in Occupational Health, Dept. of Occupational Health Engineering, School of Health, Lorestan University of Medical Sciences, Khorramabad, Iran.
2. Faculty Instructor, Dept. of Occupational Health Engineering, School of Health, Lorestan University of Medical Sciences, Khorramabad, Iran; Ph.D Student in Occupational Health, Dept. of Occupational Health Engineering, Faculty of Medical Sciences, Trabiat Modares University, Tehran, Iran.
3. Assistant Prof., Social Determinants of Health Research Center, Dept. of Occupational Health Engineering, Faculty of Health, Qazvin University of Medical Sciences, Qazvin, Iran.
4. BSc in Occupational Health, Dept. of Occupational Health Engineering, School of Health, Lorestan University of Medical Sciences, Khorramabad, Iran.
5. Assistant Prof., Dept. of Occupational Health Engineering, Faculty of Public Health, Mazandaran University of Medical Sciences, Sari, Iran.
* Corresponding author: Vida Zaroushani; E-mail: v.zaroushani@qums.ac.ir
Abstract
Background: Risk assessment is an important tool for reducing casualties and financial damage in the oil and gas industry. This research aimed to identify and evaluate process hazards in the petrochemical industry in 2016.
Material and Methods: In this case study, a team was organized and briefed on the process. Besides, hazard identification was performed using the Hazard and Operability Study. Next, causes were analyzed using the Fault Tree Analysis and occurrence probability of top events. Finally, events and subevents were ranked. The minimum cut sets were determined using Boolean algebra.
Results: A total of 77 events were identified. Accordingly, unacceptable, tolerable, and acceptable risk levels were 41, 31, and 5 events, respectively. Fire was the most unacceptable risk level, with the final events of "human errors in correct gasket installation on the flange surface" and "flange defects" having had the shares of 51.2 and 21.55%, respectively.
Conclusion: The combination of the two HAZOP and FTA techniques is useful in process industries in which incomplete performance of the system and control systems is the most effective factor in the potential occurrence of fire. Human errors and flange defects are the two main factors in this event, so occupational safety and health must be improved in this system. Thus, due to complex interactions between humans, machines, materials, and the environment in systems, such as the petrochemical industry, which lead to uncertainties in safety results of the process, risk assessment is recommended to be performed periodically using different techniques.
Keywords: Safety, Chemical Hazard Release, Chemical Safety, Safety Management.
Introduction
Growth in human populations with the increase in industries have raised risk potentials and accidents. Particular attributes of the oil and gas industry, including its vastness, huge volume of capital, numerous dangers, and high number of employees have attracted the attention of safety experts, which demand their extensive efforts to improve the level of safety in this industry [1, 2].
The presence of hazardous chemicals and operating units under conditions of high temperature and pressure, including reactors and storage tanks in the chemical industry, has raised the possibility of accidents, such as explosions and fires. In this industry, events occur even in industrial units with most up-to-date designs and most experienced employees [3, 4]. The occurrence of several fires and explosions in 2016 in Iranian petrochemical plants, including Shahid Tondgooyan, Maroon, Bandar Imam Khomeini, Mahshahr, and Bouali Sina, showed that inattention to safety considerations could lead to catastrophic human and financial losses within a short time. Thus, there is still a need for comprehensive efforts to prevent similar incidents in the future [5].
Given the incidents in process industries and their damage to humans and the environment, systematic risk assessment, as an effective tool, is widely used to manage safety in process industries [4].
Some methods, such as Hazard and Operability Study (HAZOP) and Fault Tree Analysis (FTA), are specifically used to identify and assess hazards in process industries [3, 6].
In many previous studies, a complex of HAZOP and FTA methods was used to assess safety, health, and environmental hazards and to identify potential hazards in chemical plants. It was also used to identify causes and consequences of possible fault forms under abnormal conditions as most important factors in the occurrence of chlorine leakage in drinking water systems [3, 7-9].
HAZOP is the most well-known and reliable method for qualitatively identifying potential hazards in process industries. This method covers all phases of the life cycle of a plant or equipment, including idea stages, location selection, component design, construction, installation, implementation, operation, decommissioning, and dismantling [3, 7].
Fault tree analysis is a quantitative, logic, and geometric tool for extracting and interpreting root causes in the relationship between component defects, which is used to evaluate the probability of an accident, as a result of the sequence or combination of faults and defects [6, 8, 10]. In this method, all events leading to potential dangers are discovered using Boolean algebra [11].
Given the lack of similar research in the petrochemical industry and the necessity for determining potential hazards through root cause analysis and evaluating the probability of top events, this study was conducted to prepare technical data for safety and health management.
Materials and Methods
The present study is a case study of risk assessment using HAZOP and FTA methods, which was conducted in the Butene-1 unit in the Khorramabad petrochemical industry in 2016 through research project number 1889. In the first step, an expert team was organized and data collection was conducted through direct observation, interviews with HSE unit officials, room control, site experts, and via studying P and ID as well as PFD maps, while the performance of equipment and potential hazards were investigated.
This unit was selected for risk assessment given the presence of catalysts and highly hazardous materials under conditions of high temperature and pressure in the Butene-1 unit. These conditions could lead to catastrophic accidents, such as fire and explosion. The HAZOP method was used to identify potential hazards of the unit.
HAZOP is an effective and systematic method for identifying risks and operational problems in the system and determining their effects. In addition, it is a qualitative study that identifies deviations from the design, which evaluates its causes and consequences [3]. In this method, after formation of a team of experts, familiarizing them with the production process in the unit under investigation, and identification of the nodes, operating parameters (pressure, flow, composition, temperature, and level of liquids) were considered, and their deviations and possible consequences were examined. Next, the Fault Tree Analysis technique was used to determine top events and occurrence probabilities, and to illustrate the path of risk formation [6].
It is worth noting that after choosing the top events, the causes of their occurrence were defined as middle events, with these events analyzed until the final event was determined [6].
After plotting the fault tree, the events were named, and the minimum cut was determined using Boolean algebra [11]. Next, the occurrence probability of the base events was determined based on the company's records and expert opinions. In the absence of the occurrence probability of base events, the occurrence probability of the base events was calculated based on the failure rate per year (λ) according to Eq. (1) and assuming t = 1 (one year) [12] as follows:
Eq. (1). P=1-e-λt
Next, probabilistic relationships between input and output events as well as gates were used to calculate the occurrence probability of the main event in the minimum cuts. After calculating the occurrence probability of the top event, the failure rate was calculated per year [12] by defining it in Eq. (2):
Eq. (2). λ= - Ln (1-P)
One of the major parts of risk assessment is the calculation of risk levels and determination of tolerance of top events. Thus, the risk matrix of the ISO-17776 standard was used to determine the risk level of events. Table 1 shows the risk matrix of this standard [13] as follows:
Table 1. The risk matrix based on the ISO-17776 standard
Repeatability/probability |
Consequences |
||||||||
E |
D |
C |
B |
A |
Reputation |
Environment |
Assets |
Persons |
Severity ranking |
It happens several times a year in the region. |
It happens several times a year in the company |
It has not already happened in the company |
It happens several times a year in the company |
It rarely happens in the company |
|||||
|
|
|
Without impact |
Without impact |
Without damage |
Without damage |
0 |
||
Little impact |
Minor impact |
Minor damage |
Mild injury |
1 |
|||||
|
Limited impact |
Little impact |
Low damage |
Low damage |
2 |
||||
|
|
Significant impact |
Local impact |
Local damage |
Major damage |
3 |
|||
|
|
Major national impact |
Major impact |
Serious damage |
A death case |
4 |
|||
Intolerable |
|
Major international impact |
Wide-range impact |
Severe damage |
Multiple deaths |
5 |
In the next step, for events of an unacceptable level, the occurrence probability of their subevents (events occurring immediately in the bottom gate of the top event) was computed. Next, the events were ranked, with the share of each event in the occurrence of the event determined. One of the major outputs of the fault tree analysis is the ranking of the importance of end events. Thus, the end events were ranked using the proposed formula as shown in Eq. (3) [12] as follows:
Eq. (3): IA = ∑+U a /∑+Us
Where the IA, ∑Ua, and ∑Us indicate importance of end event A in creating the main event, the sum of the occurrence probability of minimal cuts in which event A exists, and the occurrence probability of the main event, respectively.
Results
The present study was conducted to assess the
risk of hazards using the HAZOP and FTA methods, which were identified through HAZOP implementation in a total of 59 nodes and 123 hazards. The hazards identified using the HAZOP method were used to determine top events using the FTA method. In the present study, a total of 77 risks were investigated using the FTA method. Among them, there were 41 risks with an intolerable level, 31 risks with a tolerable level, and 5 risks with an acceptable level based on the risk matrix of the ISO-17776 standard table 1 [13].
Findings from evaluation of the causes of the identified risks in the HAZOP method showed that 46.84% of the risks were due to "incomplete performance of the system and control systems", 30.38% were related to "system equipment defects", and 22.78% were related to "human errors". Table 2 shows one of the completed HAZOP worksheets.
Table 2. A sample worksheet of a completed hazard and operability study in a petrochemical industry unit
HAZOP worksheet |
|||||||
Study title: Risk assessment using the HAZOP method in a petrochemical industry unit |
Date: |
Team members: |
|||||
Examined section (node): re- exit and entry of butane to the drum |
|||||||
Unit components: flanges, pumps, pipelines |
|||||||
No. |
Keywords + operational parameters |
Reason |
Consequence |
Available shields |
Recommended control measures |
Responsibility for implementation |
|
1 |
Lower flow |
- Leakage in the flange drum |
Fire |
- Installing a detector in different parts of the operational site |
1- Periodical inspection of flanges and gaskets |
Cite man/ HSE unit management |
|
According to the results of the HAZOP study, the corresponding fault tree diagrams were drawn. Due to the large number of fault tree runs and impossibility of introducing all of them in this paper, two of them have been shown in Figs. 1 and 2